HomeMy WebLinkAboutCC Reso 2026-56 - Adopting Conflict of Interest Code for Design-Build Construction ProjectsRESOLUTION NO. 2026-56
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF UKIAH ADOPTING AN
ORGANIZATIONAL CONFLICT OF INTEREST CODE FOR DESIGN -BUILD
CONSTRUCTION PROJECTS
WHEREAS:
1. Procuring design -build contracts for construction of projects in the City is a valuable option;
and
2. Public Contract Code section 22162(c) requires the City to develop guidelines for a standard
organizational conflict -of -interest policy that can be incorporated into and applied in soliciting
proposals for design -build projects;
NOW, THEREFORE, BE IT RESOLVED as follows:
Organizational Conflict of Interest Policy Applicable to Design -Build Projects
1. Purpose
The purpose of this Organizational Conflict of Interest Policy ("Policy") is to establish the City of
Ukiah's organizational conflict of interest guidelines applicable to design -build projects procured
pursuant to Public Contract Code section 22160, et seq. and Federal Procurement Standards 2
CFR 200.319.
2. Authority
By this Policy, the City Manager, or his/her designee, of the City (Ukiah) is delegated the
authority to make the City's final determination on whether any Proposers have an
Organizational Conflict of Interest in a manner consistent with the City Council's general and
specific intent set forth herein, consistent with all applicable laws, and in consultation with the
City Attorney.
The legal basis for this policy is Public Contract Code Sections, 22160-22169, as may be
amended from time to time, and such other statutory and regulatory provisions as may be
applicable.
3. Policy
Contractors and Consultants participating as proposers on a design -build project or joining a
design -build team ("Proposers") may not have organizational conflicts of interest.
3.1 Organizational Conflict of Interest Defined
Page 1 of 4
Organizational conflicts of interest are circumstances arising out of a Consultant's or
Contractor's existing or past activities, business or financial interests, familial relationships,
contractual relationships, and/or organizational structure (e.g., parent, entities, subsidiaries,
affiliates) that results in:
(i) impairment or potential impairment of a Consultant's or Contractor's ability to
render impartial assistance or advice to the City or of its objectivity in performing
work for the City;
(ii) an unfair competitive advantage for any bidder or proposer with respect to a
City procurement; or
(iii) a perception or appearance of impropriety with respect to any of the City's
procurements or contracts or a perception or appearance of unfair competitive
advantage with respect to a procurement by the City (regardless of whether any
such Exhibit A 2 perception is accurate).
While this Policy cannot and does not purport to describe every problematical situation that may
arise, the following are examples of circumstances that will constitute an organizational conflict
of interest:
3.1.1 A Proposer is the City's general engineering or architectural Consultant to the
design -build project, except that a subconsultant to the general engineering or
architectural Consultant that has not yet performed work on the contract to provide
services for the design -build project may participate as a proposer or join a design -build
team if it terminates the agreement to provide work and provides no work for the City's
general engineering or architectural Consultant on the design -build project.
3.1.2 A Proposer has assisted or is assisting the City in the management of the design -
build project, including the preparation of the request for proposals, evaluation criteria, or
any other aspect of the procurement.
3.1.3 A Proposer has conducted preliminary design services for the design -build project
such as conceptual layouts, preliminary design, or preparation of bridging documents.
3.1.4 A Proposer performed design work related to the design -build project for other
stakeholders in the design -build project.
3.1.5 A Proposer performed design work on a previous contract that specifically excludes
it from participating as a proposer or joining a design -build team for the design -build
project.
3.1.6 A Proposer is under contract with any other entity or stakeholder to perform
oversight of the design -build project. 0
Page 2 of 4
3.1.7 A Proposer has obtained advice from, or discussed any aspect relating to the
design -build project or procurement of the design -build project with, any person or entity
with an organizational conflict of interest, including, but not limited to, the Consultants of
any entity that have provided technical support on the design -build project.
3.1.8 Any circumstances that would violate California Government Code Section 1090,
et seq. or the Political Reform Act, Government Code Section 80000, et seq.
3.2 Proposers' Obligations Before Contract Award
If a Proposer determines that a conflict of interest or potential conflict of interest exists,
Proposers must immediately make a full written disclosure of the conflict or potential conflict of
interest to the Purchasing Officer of the City and shall have a continuing obligation to do so until
they are no longer Proposers.
Such disclosure will not necessarily disqualify a Proposer from being awarded a contract,
however, the Proposer shall propose measures to avoid, prevent, or mitigate all potential or
actual conflicts. The City Manager, or his/her designee, shall determine whether the proposed
measures are sufficient to overcome the conflict or potential conflict and whether the Proposer
may continue with the procurement process. In the event the conflict of interest involves the City
Manager, or his/her designee, the City Attorney would make the determination.
3.3 Proposers' Obligations After Contract Award
The successful Proposer to whom a contract is awarded ("Contractor") has an ongoing
obligation to monitor and disclose its conflicts or potential conflicts of interest. The City has a
right to ongoing enforcement of this Policy. If an organizational conflict of interest is discovered
after contract award, the Contractor must make an immediate and full written disclosure to the
City Manager, or his/her designee, that includes a description of the action that the Contractor
has taken or proposes to take to avoid or mitigate such conflicts. If an organizational conflict of
interest is determined to exist and the Contractor was or reasonably should have been aware of
an organizational conflict of interest prior to award of the contract while acting with due diligence
to search for such a conflict and did not disclose the conflict, the City may terminate the
contract, and Contractor shall disgorge all money paid to it under the Contract, in addition to any
other remedies available to the City. If a new conflict of interest arises after contract award, and
Contractor's proposed measures to avoid or mitigate the conflict are determined by the City to
be inadequate to protect the City, the City may terminate the contract. If the contract is
terminated, the City assumes no obligations, responsibilities and liabilities to reimburse all or
any portion of the costs incurred or alleged to have been incurred by Contractor and the City
further is entitled to pursue any and all available legal remedies.
4. Incorporation By Reference
Page 3 of 4
This Policy shall be incorporated by reference into all related Consultant and Contractor design -
build solicitations and contracts executed by the City.
PASSED AND ADOPTED this 151' day of July, 2026, by the following roll call vote:
AYES:
Councilmembers Crane, Rodin, Criss, Orozco, and Mayor Sher.
NOES:
None.
ABSENT:
None.
ABSTAIN:
None.
ATTEST:
Araceli Sandoval, Deput City Clerk
L�-t� 2L
Susan Sher, Mayor
Page 4 of 4