CITY OF UKIAH
AMENDMENT NO. 3
TO
PROFESSIONAL SERVICES AGREEMENT
BETWEEN
REN ALEXANDER DESIGN and THE CITY OF UKIAH
This Amendment No. 3, entered on February 11, 2025, revises the Agreement for
Professional services dated March 31, 2022, between the City of Ukiah and Ren
Alexander Design for professional consulting services relating to providing architectural
services and plans for the interior of the Electric Service Center at Hastings.
This Amendment No. 3 adds an additional $1,500, as described in Exhibit 1. This revises
the total, not-to-exceed amount to $99,600.
Except as expressly amended by this Amendment, all other terms remain unchanged and
in full force and effect.
IN WITNESS WHEREOF, THE PARTIES HAVE EXECUTED THIS
AMENDMENT ON THE EFFECTIVE DATE:
CONSULTANT
BY: DATE:
PRINT NAME:
CITY OF UKIAH
BY: DATE:
SAGE SANGIACOMO, CITY MANAGER
ATTEST
BY: DATE:
KRISTINE LAWLER, CITY CLERK
02/11/24
Steven Ratley
02/13/2025
Kristine Lawler (Feb 13, 2025 15:19 PST)
Kristine Lawler 02/13/2025
Exhibit 1
R E N I A L E X A N U E R Ukiah Electric Service Center Lt:Change Order Request
r
Change Order Breakdown
Feb 2025 [CA] (1)+OAC onsite,(1)Punch List walk,Substantial completion: 10 $150 $1,500,00
Reviewing and responding to any outstanding items for fina
inspection sign off,Final Contractor Pay Application Review
Total Change Order Request *NTE $1,500.00
*Projected Construction Substantial Completion on Feb 17 2025(bated Jon,28,2025)Estimates bored off of hourly services
provided for previous months of Construction Administration services.
Impact on Schedule: No
Cost Impact:
Orig nal Contract Amount: $82,500.00
Contract Amendment 2 dated July 22, 2024 $15,600.00
C.O.R#2 dated 02/01/2025 $1,500.00