This Amendment No. 7, entered on September 18, 2024, revises the Agreement for
professional services dated March 21,2019,between the City of Ukiah and Mintier Harnish
for professional consulting services relating to professional planning services for a General
Plan Update, Environmental Impact Report, and other related advanced planning services.
This Amendment No. 7 adjusts the scope of work, as outlined in Exhibit 1,by adding and
deducting certain tasks, with no impact on the current total not to exceed contract amount
of$775,968.
Except as expressly amended by this Amendment, all other terms remain unchanged and
in full force and effect.
IN WITNESS WHEREOF, THE PARTIES HAVE EXECUTED THIS
AMENDMENT ON THE EFFECTIVE DATE:
MINTIER HARNISH
BY: DATE:
�q= 9/18/2024
JIM HARNISH, JD
CITY OF UKIAH
BY: 5S DATE: Sep 30, 2024
SAGE SANGIACOMO, CITY MANAGER
ATTEST
A,,&,,-� Sep 30, 2024
BY. Kristine Lawler 30,2024 09*59 PDT) DATE:
KRISTINE LAWLER, CITY CLERK
EXHIBIT 1
Rincon Consultants, Inc.
66 Franklin Street,Suite 300
Oakland,California 94607
I
510-834-4455
September 16, 2024
Rincon Project No. 24-15600
Blake Adams, Chief Resilience Officer
City of Ukiah
300 Seminary Ave., Ukiah, California 95482
Via email: badams@cityofukiah.com
Cc: cschlatter@cityofukiah.com;jim@mintierharnish.com
Subject: Ukiah Climate Action Plan + Initial Study-Negative Declaration Scope Change Proposal
Per City of Ukiah (City) request, Rincon Consultants, Inc. (Rincon) is submitting this scope change proposal to
1) add scope for additional Climate Action Plan (CAP) project management and meetings time with City staff
as well as to 2) deduct scope related to attendance at public meetings. The following section details the
specific tasks that make up this scope change proposal. Below we explain the adjustments related to existing
contract tasks.
Added Scope of Work
Task 1.2 Project Management and Meetings
The original scope/budget assumed a project timeline of 10 months of project management and
administration time as well as up to 18 30-minute MS Teams meetings.Specifically,this scope/budget change
now instead assumes a project timeline of 13 months of project management and administration time(project
kickoff was beginning of April 2024 and CAP adoption is anticipated for end of April 2025) as well as up to 13
60-minute MS Teams meetings. Note that 6 60-minute MS Teams meetings have already occurred on June
18, July 16, July 30, August 6, August 20, and September 3. Therefore, we now have 7 60-minute MS Teams
meetings remaining. We anticipate these remaining meetings will occur through December 2024 while the
Draft CAP measures/actions list is finalized, the balancing act survey is prepared and distributed, the Draft
CAP measures/actions quantification/substantial evidence report is prepared and submitted for City review
by November, and the Administrative Draft CAP document is prepared and submitted for City review by
December.
Deducted Scope of Work
Task 4.1 Community Workshops and Online Survey
Rincon will deduct attendance and preparation for the 2nd community workshop.
Task 4.3 Sustainability Working Group Focus Session
Rincon will deduct attendance and preparation for the sustainability working group focus session.
Task 4.4 CAP Public Hearings
Rincon will deduct attendance and preparation for both CAP public hearings.
Task 6.5 IS-ND Hearing + NOD
Rincon will deduct attendance and preparation for the IS-ND adoption hearing.
www.rinconconsultants.com
City of Ukiah
CAP+IS-ND
Scope Change Proposal
Schedule and Cost
Rincon anticipates the work scope changes presented in this proposal would occur through April 2025. The
costs related to the added and deducted tasks described in this proposal are presented in Table 1 below.
Table 1 Scope Change Proposal Cost Summary
Task Estimated Cost
Task 1.2:Project Management and Meetings $9,442
Total Additions $9,442
Task 4.1:Community Workshops&Survey -$2,036
Task 4.3:Sustainability Working Group Session -$2,036
Task 4.4 CAP Public Hearings -$4,322
Task 6.5 IS-ND Hearing+NOD -$1,048
Total Deductions -$9,442
TOTAL NET CHANGE COST $0
All work would be performed in accordance with the work scope outlined above and the terms and conditions
in the existing original contract between Mintier Harnish and Rincon dated April 2, 2024. Additional services
beyond those identified herein would be provided, at the City's request, on a time and materials expense
reimbursement basis in accordance with Rincon's 2024 standard fee schedule (see attached). No other
services would be provided without the City's express written authorization. This scope change proposal cost
estimate is in effect for a period of 30 days during which time the elements of this proposal are negotiable to
meet the needs of the proposed updated work scope. To authorize, please reply all to provide approval in
writing of this scope change proposal, so that Mintier Harnish can provide a corresponding no-cost scope
amendment to their April 2, 2024 agreement with Rincon.
Thank you for your consideration and for this opportunity to support your sustainability and environmental
planning efforts with this updated work scope. If you have questions regarding this proposal, please contact
Kelsey Bennett at kbennett@rinconconsultants.com.
Sincerely,
Rincon Consultants, Inc.
/Q7S _ _
Kelsey Bennett, MPA, LEED-AP
Environmental/Sustainability Director
kbennett@rinconconsultants.com
Attachments
Attachment 1 Rincon 2024 Fee Schedule
2
i Rincon Consultants, Inc.
Standard Fee Schedule for Environmental Sciences and Planning Services
Professional,Technical and Support Personnel* January 1,2024- December 31,2024
Senior Principal $319
Principal $307
Director $307
Senior Supervisor II $292
Supervisor 1 $272
Senior Professional 11 $255
Senior Professional 1 $238
Professional IV $211
Professional 111 $196
Professional 11 $174
Professional 1 $155
Associate 111 $130
Associate 11 $117
Associate 1 $109
Field Technician $94
Data Solutions Architect $196
Senior GIS Specialist $187
GIS/CADD Specialist II $167
GIS/CADD Specialist 1 $150
Technical Editor $147
Project Accountant $125
Billing Specialist $107
Publishing Specialist $120
Clerical $107
*Professional classifications include environmental scientists,urban planners,biologists,geologists,marine scientists,GHG verifiers,
sustainability experts,cultural resources experts,and other professionals.Expert witness services consisting of depositions or in-court
testimony are charged at the hourly rate of$400.
Reimbursable Expenses
Direct Cost Rates
Photocopies- B/W $0.25(single-sided),$0.45(double-sided)
Photocopies-Color $1.55(single-sided),$3.10(double-sided)
Photocopies- 11"by 17" $0.55(B/W),$3.40(color)
Oversized Maps $8.50/square foot
Digital Production $15/CD,$20/flash drive
Light-Duty and Passenger Vehicles* $90/day
4WD and Off-Road Vehicles* $150/day
*Current IRS mileage rate for mileage over 50 and for all miles incurred in employee-owned vehicles.
Direct Costs.Other direct costs associated with the execution of a project,that are not included in the hourly rates above,are billed
at cost plus 16%.These may include,but are not limited to,laboratory and drilling services,subcontractor services,authorized travel
expenses, permit charges and filing fees, mailings and postage, performance bonds, sample handling and shipment, rental
equipment,and vehicles other than covered by the above charges.
Annual Escalation.Standard rates subject to 3.5%annual escalation,on January 1.
Payment Terms.All fees will be billed to Client monthly and shall be due and payable upon receipt or as indicated in the contract
provisions for the assignment. Invoices are delinquent if not paid within 10 days from receipt or per the contractually required
payment terms.
Effective January 1,2024