This Amendment No. 2, entered on July 22, 2024, revises the Agreement for Professional
services dated March 31, 2022, between the City of Ukiah and Ren Alexander Design for
professional consulting services relating to providing architectural services and plans for
the interior of the Electric Service Center at Hastings.
This Amendment No. 2 adds an additional $15,600, as described in Exhibit 1. This
revises the total, not-to-exceed amount to $98,100.
Except as expressly amended by this Amendment, all other terms remain unchanged and
in full force and effect.
IN WITNESS WHEREOF, THE PARTIES HAVE EXECUTED THIS
AMENDMENT ON THE EFFECTIVE DATE:
CONSULTANT
BY: DATE:
PRINT NAME:
CITY OF UKIAH
BY: DATE:
SAGE SANGIACOMO, CITY MANAGER
ATTEST
BY: DATE:
KRISTINE LAWLER, CITY CLERK
07/22/24
Steven Ratley
Aug 19, 2024
Aug 21, 2024
REN / ALEXANDER Ukiah Electric Service Center T.I: Change Order Request
CHANGE ORDER REQUEST
Hello Cindy,
We are writing to formally request a Change Order to address Construction Administration services
required for the ongoing tenant improvement project at 1350 Hastings Ave.
As we progress through construction we project to bill to the total original contract sum within the
next four to six weeks.
This is in part due to a number of factors, including previously billed Additional Services during the
Construction Documents phase and the Bidding & Negotiation phase. As requested, additional hours
spent during these phases were billed as worked toward the base contract. The combination of
existing building conditions and the fire and water damage are necessitating more time spent
providing responses to RFI’s, supplemental information/ sketches and coordination during
Construction.
To maintain the quality and integrity of the project while adhering to the proposed schedule, we
respectfully request a Change Order to cover additional Construction Administration costs. This
Change Order will ensure that the Ren / Alexander can continue to provide the required level of
oversight and support for the team to successfully complete the project.
Thank you very much for your time and consideration. Please find below the details of the proposed
Change Order for your review and approval on the following page.
Sincerely,
Page of 1 2
Project: Ukiah Electric Service Center T.I Date: 6/11/2024
To:
Cindy Sauers
City of Ukiah Electric Utility Director
1350 Hastings Avenue
Ukiah, CA 95482
From:
Steven Ratley & Kali Gordon
Ren / Alexander Design
301 Scott Street
Ukiah, CA 95482
Steven Ratley
Principal / Architect
Ren / Alexander Design
[Architect - CA Lic. C-39696]
EXHIBIT 1
REN / ALEXANDER Ukiah Electric Service Center T.I: Change Order Request
Impact on Schedule: No
Cost Impact:
Original Contract Amount: $82,500.00
Cost of Change in Services for Construction Administration: $15,600.00
Change Order Breakdown
Jul 2024 [CA](2) - OAC’s onsite or remote / Site Observation
Reviewing and responding to RFI’s, Submittals, Change Orders and
providing Architectural Sketches (SK’s) ( Assumed 2hrs per review/
response @ 10 Items)
Monthly Contractor Pay Application Review
26 $150 $3,900.00
Aug 2024 [CA](2) - OAC’s onsite or remote / Site Observation
Reviewing and responding to RFI’s, Submittals, Change Orders and
providing Architectural Sketches (SK’s) ( Assumed 2hrs per review/
response @ 10 Items)
Monthly Contractor Pay Application Review
26 $150 $3,900.00
Sep 2024 [CA](2) - OAC’s onsite or remote / Site Observation
Reviewing and responding to RFI’s, Submittals, Change Orders and
providing Architectural Sketches (SK’s) ( Assumed 2hrs per review/
response @ 10 Items)
Monthly Contractor Pay Application Review
26 $150 $3,900.00
Oct 2024 [CA](2)+ OAC’s onsite, Punch List walk, Substantial completion
Reviewing and responding to RFI’s, Submittals, Change Orders and
providing Architectural Sketches (SK’s) ( Assumed 2hrs per review/
response @ 10 Items)
Final Contractor Pay Application Review
26 $150 $3,900.00
Total Change Order Request *NTE $15,600.00
*Projected Construction Substantial Completion on Oct 16 2024. Estimates based off of hourly services provided for previous
months (April, May + June) of Construction Administration services.
Page of 2 2