Loading...
HomeMy WebLinkAboutGHD, Inc. 2021-10-13; Amendment 2 2023-01-19CITY OF UKIAH AMENDMENT NO. 2 TO PROFESSIONAL SERVICES CONTRACT 2122118 BETWEEN GHD INC and THE CITY OF UKIAH This Amendment No. 1, entered on January 19, 2023, revises the Agreement for Consulting Services for preparing the plans, specifications and estimate for the Great Redwood Trail Phase 4 (GRT 4) Project dated October 13, 2021 between the City of Ukiah and GHD Inc, as follows. 1.Add additional environmental studies and permitting to the Scope of Work, per attached Exhibit 1. 2.Revising the guaranteed maximum dollar amount by an additional $61,958.00 for professional consulting services related to the design of the GRT 4, for a revised, total contract amount not-to-exceed $424,267.00 Except as expressly amended by this Amendment, all other terms remain unchanged and in full force and effect. IN WITNESS WHEREOF, THE PARTIES HAVE EXECUTED THIS AMENDMENT ON THE EFFECTIVE DATE: GHD INC BY: DATE: PRINT NAME: CITY OF UKIAH BY: DATE: SAGE SANGIACOMO, CITY MANAGER ATTEST BY: DATE: KRISTINE LAWLER, CITY CLERK Matthew G. Kennedy, PE January 20, 2023 COU No. 2122-118-A2 Jan 27, 2023 Kristine Lawler (Jan 27, 2023 08:51 PST) Kristine Lawler Jan 27, 2023 The Power of Commitment GHD Inc. 12557341 City of Ukiah Ref: COU No. 2122118 Our ref: 12557341 November 7, 2022 Tim Eriksen Public Works Director / City Engineer City of Ukiah 300 Seminary Avenue Ukiah, CA 95482 RE: Great Redwood Trail Phase 4: Amendment No. 2 for Additional Design and Environmental Services Dear Mr. Eriksen: This letter proposal is submitted based on our additional efforts to complete the project and address changes to the design which resulted from the alignment of the trail shifting from being located along the centerline of the tracks as originally proposed to being offset to the east of the tracks. The decision to shift the alignment to the east side of the tracks was based on the City’s concern should railbanking not be approved by the California Utilities Commission (CUC). The result of shifting the trail to the east of the tracks introduced a number of additional design and environmental requirements. These issues are generally related to grading, drainage, structural, tree removal and wetlands. These issues are interwoven with the environmental and resource agency permitting. Addressing environmental and resource agency permitting was added to the project by Amendment No. 1, but coordination efforts and requirements from the resource agencies have been greater than anticipated. Below is a summary of the tasks and efforts we have that are in addition to the original approach, scope of work and the amendment for environmental and permitting: 1. Bridge and Abutment Designs: The Scope of Work assumed the existing bridges and foundations could be reused with minor modifications for the trail, such as replacing the decks. o Shifting the trail to the east of the tracks meant designing two new bridges, including efforts to coordinate the bridge foundations and related grading with existing nearby utilities. 2. Retaining Wall Designs: The Scope of Work assumed no new retaining walls would be required since the alignment was to be on the track alignment. o Shifting the trail to the east of the tracks meant designing cast-in-place concrete and mechanically stabilized earth (MSE) retaining walls as part of the trail cut/fill grading. 3. Parking Lot Design at the Animal Shelter. Design “off-site improvements” would not have been needed if the trail alignment was along the rail alignment. o Shifting the trail to the east of the tracks impacted the parking lot at the animal shelter on Plant Road. The design includes demolition of the existing parking lot, and new paving and parking layout to accommodate the trail to the east of the tracks. 4. Impact analysis for moving the trail back on the rail o We did an analysis and cost estimate for this scenario, but it was abandoned and we returned to the current alignment 5. Earthwork and Grading Design: Design of grading, cuts and fills was expected to be minimal with the trail alignment along the tracks. Some minor fill was expected to address the proposed width of the trail and shoulders. o Shifting the trail east of the tracks resulted in significant additional design efforts related to grading, trail profile, trail alignment, and earth retaining systems (previously summarized). This effort included: Design of trail alignment offset from track centerline. Design of new cuts and fills for a smooth trail profile. EXHIBIT 1 12557341 | Proposal for Environmental Studies and Permitting 2  Designing to minimize/balance the earthwork (cuts and fills).  Designing to avoid mapped wetlands (to the extent possible/practical) 6. Additional Environmental and Permitting: o Amendment 1 assumed no field review meetings with resource agencies would be needed. We attempted to consolidate these to one site visit for both RWQCB and CDFW, but it didn’t work with the agencies’ schedules. To date we have coordinated and attended two field meetings for wetlands with the RWQCB and CDFW. Additional coordination efforts and confirmation of mitigation is still expected. It’s possible that USACE may also ask for a site visit. o In February 2022, when Amendment 1 for environmental support was submitted to the City, a federal district court had in the fall of 2021 rescinded the Trump-era Pre-filing Rule for Water Quality Certifications with the Regional Board. In April 2022, after the Amendment was approved, the Supreme Court struck down the District Courts ruling thus re-instating the Pre-filing Rule. GHD’s scope of work did not include support for the Pre-filing process which we are currently navigating with the RWQCB. 7. Wetland Mitigation Design: Wetlands will be impacted by the trail alignment east of the tracks, and design of wetland mitigation measures was not included in the original Scope of Work or Amendment 1. o We assumed mitigation in the form of enhancement and restoration would suffice. While proposed enhancement and restoration has been deemed acceptable for the fill impacts to Waters, the RWQCB has requested creation of new wetland areas for the impacts to existing wetlands. o GHD prepared wetland mitigation design along the west side of the rail, including new wetland grading, detailing, specifying seed mix, etc. o The culvert extensions have triggered more detailed permit review by the CDFW, resulting in more coordination and design efforts. 8. Tree Impacts: Few to no impacts to existing trees were expected when the trail was on the rail alignment. o Moving the trail alignment east of the tracks required that additional detailing in accounting of tree impacts and protection measures and reflecting them on the plans. 9. Base and Alternate Bids: Development of base and additive/deductive bid alternates was not included in the Scope of Work. Shifting the trail alignment east of the tracks has increased the cost of the project. o The City requested GHD formulate the bid to specify a base bid from Commerce Drive south to Norgard Lane, and an additive bid alternate from Norgard Lane south to Plant Road. The segment of trail south of Plant Road was removed from the project due to cost. This effort included creating a base and additive bid alternate schedule and adding notes and callouts to the plans to indicate the limit of base and alternate bid item work. 10. Landscape Redesign: Alta Planning + Design needed to redesign areas of landscaping to address waters mitigation requirements that were discovered after the jurisdictional delineation effort associated with Amendment 1. Planting locations and species choices had to be adjusted to balance both the needs of the grant as well as waters enhancement mitigation. 11. Revise Permit Applications: The initial draft applications included the original 1.9-mile trail segment. This was later revised after the portion of the project south of Plant Road was removed. GHD went back through the applications to remove references to that portion of the proposed trail south of Plant Road. The design is essentially complete, pending any comments from the City. Work remaining to finalize the bid package includes additional resource agency coordination and permitting, bridge and culvert hydraulic analysis and finalizing the design, finalizing the base and alternate bid items, and finalizing the technical specifications, bid schedules and bid package. Per City direction, this amendment request does not include the additional hydraulics analysis required for the bridge design due to the 100-yr floodplain. If the bid alternate is awarded to the Contractor GHD will need additional approval from the City to proceed with the hydraulic analysis prior to construction. FEE ESTIMATE 12557341 | Proposal for Environmental Studies and Permitting 3 The Amendment 2 budget is attached, which covers our current budget overrun of approximately $52,000, and finalize the design for bidding. GHD proposes a time-and-materials fee not to exceed $61,958 without written authorization from the City. See attachment for breakdown of the estimated fee. We appreciate the City’s consideration of this proposal and are very motivated to complete the design so the City can prepare the project for bid advertisement. Please don’t hesitate to contact me if you have any questions. Sincerely, GHD Inc. Erik Fanselau, PE Project Manager Cc: Kristine Gaspar, Matt Kennedy, PE, Principal Attachment: Fee Estimate Attachments: 1. GHD Amendment 2 Fee Proposal Attachment 1 Project Name:Great Redwood Trail Phase 4: Amendment 2 Client:City of Ukiah Prepared by:Matt Kennedy Date: Job Number:12557341 LABOR CATEGORY >Proj.Proj.Civil H/H Struct.PW Field Surveyor Env Staff CAD WP PA TOTAL Sub-TOTAL Prncpl Mngr.Eng.Eng.Eng.Survey Scientist Env Designer HOURS con- RATE >$315 $235 $195 $195 $190 $225 $195 $235 $158 $195 $135 $135 sultant(s)FEE Task / Item /Hr /Hr /Hr /Hr /Hr /Hr /Hr /Hr /Hr /Hr /Hr /Hr AMENDMENT 2 TASKS 1. Bridge and Abutment Design 1 4 50 8 63 $409.50 $12,564.50 2. Retaining Wall Design 1 4 50 8 63 $409.50 $12,564.50 3. Parking Lot Design 6 16 22 $143.00 $4,433.00 4. Impact Analysis - Trail Alignment Shift 2 4 6 $39.00 $1,289.00 5. Earthwork and Grading Design 1 20 20 41 $266.50 $8,381.50 6. Additional Environmental & Permitting 32 32 64 $416.00 $12,992.00 7. Wetland Mitigation Design 8 2 6 16 $104.00 $3,304.00 8. Tree Impacts 2 2 2 6 $39.00 $1,289.00 9. Bid Alternate 1 2 2 1 6 $39.00 $1,409.00 4 4 $26.00 $966.00 6 8 14 $91.00 $2,765.00 4 4 50 0 100 0 0 46 40 61 0 0 305 $1,982.50 $0.00 $61,957.50 4 4 50 0 100 0 0 46 40 61 0 0 305 $1,982.50 $0.00 $61,957.50 *OTHER DIRECT COSTS include printing, photocopies, shipping, vehicle mileage and other miscellaneous direct expenses. SUBTOTAL AMENDMENT 2 TASKS PROJECT TOTALS 11. Revise Permit Applications GHD - PROJECT FEE ESTIMATING SHEET November 7, 2022 LABOR COSTS FEE COMPUTATION *OTHER DIRECT COSTS 10. Landscape Redsign 11/7/2022 Page 1