HomeMy WebLinkAboutCV Larson, Company 2020-07-06; Change Order 7 2021-08-11 ORDER NO. 07
CITY OF UKIAH DATE: August 11,2021
CONTRACT CHANGE ORDER
Contract for: Pressure Zone 2 South PZ2S Water Reservoir Replacement Project
Specification No.20-02;Contract#2021-087
Owner: City of Ukiah, 300 Seminary Avenue, Ukiah,California,95482-5400
To: C.V Larsen Co., 1846 Ludwig Avenue, Santa Rosa,CA 95407-6413
You are hereby directed to make the herein described changes from the contract plans and specifications or do the following
described work not included in the contract plans and specifications:
Change requested by: City Engineer
ESTIMATED ESTIMATED
Description of Changes- Itemized Breakdown DECREASE To INCREASE To
Contract Amount Contract Amount
Project Baseline Schedule:
Notice to Proceed (August 27, 2020), Article 1 of the Agreement states the
contractor shall complete the work no later than March 4,2021. Due to project
design and construction revisions, equipment and material lead times, the
construction schedule of the project requires postponement of a construction
completion date for the crew to perform all actual work required. $0.00
City approved and directed Change Order 1-5 added a total of 130 of mixed
calendar and working days,extending the project end date to August 24,2021.
The delivery and the installation of the tank is scheduled to begin August 16,
2021. The Contractor and the Engineering staff propose an additional 30
working days to complete the project on or before October 5, 202 t.The City
project team agrees and approves.
ESTIMATED NET CHANGE IN CONTRACT PRICE $0.00
The amount of the Contract will be(deereased/iwefeased/unchanged) by $0.00
the estimated sum of:
The contract total including this and previous Change Orders will be: $775,951.07
The contract period provided for completion will be 30 Working Days
(increased ):
This change order constitutes full and complete compensation for all labor equipment, materials,overhead,profit,any and all
indirect costs,and time adjustments required to perform the above described change.
Recommended By: J1 Avr 2oz l
Lasa
s '
City Uk' h DAIL
1
Approved By:
se y of Ukiah Date
Accepted: It 2®Z
Chris Larsen,C.V Larsen Co Date -
This information will be issued as a record of any changes to the original construction contract.