HomeMy WebLinkAboutMin 07-14-05 (Special)MINUTES OF THE UKIAH CITY COUNCIL
Special Joint Meeting of the Ukiah City Council
And Ukiah Valley Sanitation District
Thursday, July 14, 2005
The Ukiah City Council met at a Special Joint Meeting with the Ukiah Valley
Sanitation District (UVSD) on July 14, 2005, the notice for which had been legally
noticed and posted, at 4:00 p.m. in the Civic Center Council Chambers, 300
Seminary Avenue, Ukiah, California. Roll was taken and the following
Councilmembers were present: Crane, McCowen, Rodin, Baldwin, and Mayor
Ashiku. Staff present: City Manager Horsley, City Attorney Rapport, Public
Utilities Director Ziemianek, and Recording Secretary Elawadly. Ukiah Valley
Sanitation District Board Members present: Crane and Board Chairman
Delbar. Absent: Board member Wattenburger. Aisc present: Chief Deputy
County Counsel Zotter, Deputy Clerk of the Board/District Secretary Rau.
2. SPECIAL MEETING OF THE CITY COUNCIL OF THE CITY OF UKIAH
AND THE BOARD OF DIRECTORS OF THE UKIAH VALLEY
SANITATION DISTRICT FOR CONSIDERATION AND POSSIBLE
ACTION ON THE KIEWIT PACIFIC COMPANY BID FOR THE
WASTEWATER TREATMENT PLANT CONSTRUCTION PROJECT
Utilities Director Ziemianek presented an overview of the Wastewater
Treatment Plant Construction project and project update since the May 18, 2005,
joint meeting of the Ukiah City Council and Ukiah Valley Sanitation District as
follows:
· Bids on the construction of the upgrade/expansion of the City's Waste Water
Treatment plant were received from Kiewit Pacific Company and Slayden
Construction, Inc. Although Kiewit Pacific Company's bid was the lowest, it
was 25.6 percent above the average amount of the Engineer's Estimate.
· Bartle Wells Associates were retained as sewer rate and bond issuance
consultants to evaluate the impact of the increased construction cost on
sewer rates. The consultants determined attempting to balance the additional
cost of the plant with "acceptable" rates for the citizens would be a difficult
challenge.
· Because the bids were higher than estimated, a subcommittee was formed to
look into specific information relevant to the bid by considering the overall
design elements, construction costs, and the cost of borrowing money.
;> The subcommittee/design engineers reviewed the associated costs
and benefits of accepting or rejecting the Iow bid.
;> The subcommittee also considered the option of re-bidding the project
and the potential effects associated with project delay and costs.
;~ The subcommittee considered the economic feasibility of cost
reductions related to design and materials.
· The subcommittee recommends the City Council, in concurrence with the
Sanitation District Board of Directors, reject all bids and plan for a re-bid
Joint Meeting of the City Council
And the Ukiah Valley Sanitation District
July 14, 2005
Page 1 of 8
process. Staff was instructed to explore cost reducing modifications to the
plans and specifications.
Mr. Ziemianek corrected the staff report to state that the target date of
December 2004 to re-bid the project should be 2005 with the bid opening
scheduled for February 2006 rather than February 2005.
Councilmember Rodin commented construction costs/materials would likely
increase if the project were delayed and inquired concerning the degree the
subcommittee considered whether a delay would be the most cost effective
approach.
Mr. Ziemianek stated the subcommittee in its analysis of the project fully
considered the potential cost effects associated with a delay and understands
that market rate conditions are difficult to project/determine. The subcommittee
also understands that the data concerning market rate conditions for the
construction industry for a specific time period will not be perfect for decision-
making purposes.
Mayor Ashiku, participating subcommittee member, addressed the
subcommittee's project analysis concerning evaluation of the risk factor in
delaying the project, and explained that overall there is greater benefit in waiting
given the timeline that has already shifted into next year's construction cycle
together with the engineering consultant's suggestions for modifications to the
overall project design.
Director Delbar inquired as to the potential interim measures other than the
chemical treatment that might be available. He stated past discussions have
considered using temporary/portable package plant systems for the interim until
the project can be completed in terms of maintaining cost efficiency. His concern
with the proposed construction timeline is whether alternative/interim systems are
necessary for efficient operation of the facility.
Mr. Ziemianek stated such interim systems/facilities have not been fully
evaluated, since the element of maintaining such systems is a consideration.
There was general discussion concerning the viability of the plant being able to
operate effectively should a decision be made to delay the improvements/update.
Mr. Ziemianek commented that a delay would allow the City the opportunity "in-
house" to thoroughly evaluate the existing and proposed new design
elements/criteria. The process would be essentially a three-fold approach to
include analysis of the engineering design, the City Council/District Board
members/subcommittee/design engineer's recommendations relative to "value-
engineering," and City staff's overall assessment. The information process and
recommendations take time.
Joint Meeting of the City Council
And the Ukiah Valley Sanitation District
July 14, 2005
Page 2 of 8
Director Delbar referred to the three possible solutions provided by Kiewit
Pacific Company:
1. To delay the decision to reject bids to allow the Council more time to find
additional funding.
2. Ask for a 60-day extension on their bid to allow for value-engineering and
design change options.
3. Award the contract to Kiewit Pacific and negotiate the value-
engineering/scope of the proiect relative to potential cost reductions and
terminate the contract if the City budget cannot be met.
Director Delbar suggested Attorney Rapport further elaborate on any potential
legal ramifications/implications associated with choosing one of these options.
Brad Kaufman/David Jack, Kiewit Pacific Company representatives, referred
to their Power Point presentation, commented on the following topics relative to
costs and delay factors:
· Current treatment plant market and their corresponding treatment plant work
schedule
· Statistical cost information regarding materials price indexes for such
materials as asphalt/cement/piping/water tubing, etc.
· Statistical data pertinent to recent Iow bid versus Engineers Estimate for
comparison purposes.
· Example of a city's timeline for update to their wastewater treatment plant
awarded to Kiewit Pacific.
· Information concerning Ukiah's bid pricing for materials, systems, landscaping
site work, electrical, and other relevant equipment necessary for the project.
· The three possible solutions referenced above.
Councilmember McCowen inquired regarding the comment made by Kiewit
Pacific representatives that it is likely they could save between 10 or 15 percent
off the bid price.
Dave Kaufman desires his company have the opportunity to demonstrate a
reduction.
Councilmember McCowen asked how the bid for Ukiah's project could have
come in over the Engineer's Estimate, which was assessed as reasonable.
Mr. Kaufman stated he has not seen the details of the estimate and is not
surprised that the engineering industries/companies typically support their
estimates.
Councilmember Baldwin commented it appears to be a contractor's market and
inquired how this factor affects Kiewit's profit margin.
Mr. Kaufman stated in past experience with six or seven bidders in competition,
their profit margins bid would typically be 25 percent less.
Joint Meeting of the City Council
And the Ukiah Valley Sanitation District
July 14, 2005
Page 3 of 8
Mayor Ashiku inquired whether Kiewit is familiar enough with Ukiah's plant that
items proposed could be eliminated without substantially affecting the outcome in
terms of the quality of the wastewater and discharge ability.
Mr. Kaufman replied his company has a list of approximately 50 or 60 items that
could be eliminated.
Councilmember Baldwin questioned in terms of cost reduction of the 50/60
items, and whether the longevity and/or durability of the project would be
affected.
Mr. Kaufman stated the items referred to pertain to alternative construction
techniques and alternate materials and would still be able to maintain the quality
and longevity of the project and design.
Councilmember Baldwin inquired why Kiewit is able to provide a list of the
items that could be eliminated as a potential cost reduction that the value-
engineering consultant could not provide.
Mr. Kaufman commented the design value-engineering consultants have the
ability to design effectively, but they do not have the cost perimeters associated
with a project.
Mayor Ashiku inquired whether Kiewit has the ability/knowledge to recommend
changes in design to enhance a particular process/system should it be
necessary/beneficial in terms of cost reduction etc., as opposed to just having the
ability to assess the cost of materials.
Mr. Kaufman replied his company has the ability to modify construction
techniques.
City Attorney Rapport commented on the City's legal aspects concerning the
options, and stated Option 3 particularly has potential legal risks. State law
requires that a process be implemented for developing/awarding a city public
works project of this magnitude. The requirements are intended to prevent
corruption and/or undue influence relative to the bidding process. State law
requires that the bids be put out in a prescribed manner where the lowest bid
from a responsible bidder is accepted or, all bids are rejected and re-bid. State
law is clear in that renegotiation of a change order before entering into a contract
or to expect a contract be awarded with the implied understanding that it is not
the project being awarded is not an option, since the project is to be significantly
modified in order to get cost reductions after the award. However, there is a
section of the Public Contract Code that allow "bid alternates/deductive bid
alternates/additive bid alternates" to be conducted in the actual bid proposal so it
becomes part of the written bid when the bid goes out. From a contract law
standpoint, if an offer to bid a project, as designed, where the bidder in response
Joint Meeting of the City Council
And the Ukiah Valley Sanitation District
July 14, 2O05
Page 4 of 8
submits a proposal to build the project to the public agency's specifications and
the public agency accepts that bid, they have explicitly agreed to build the project
as bid. And, if the public agency enters into a post-bid negotiation process and
the proposed design is not completely satisfactory, the public agency may not
legally be able to terminate the contract.
Mayor Ashiku inquired whether there are other risks involved from another
contractor suing for improper bidding.
City Attorney Rapport agreed that potential liability/risk factors, as well as the
potential for cause of action exist for another contractor involved in the bidding
process to claim the public agency undermined the bidding process and awarded
a contract at an unfair advantage.
A general discussion followed regarding the risk factors associated with the
proposed options and with deferring the project.
Councilmember Baldwin addressed the proposed new sewer rate structure,
and inquired regarding the potential for lawsuits resulting from a major spill or
malfunction of the treatment plan facility if the improvement project were delayed.
Mr. Ziemianek does not anticipate a treatment plant spill, but a detrimental
malfunction of the equipment/system could occur.
Mayor Ashiku had the opportunity to tour the treatment plant facility, including
the newly repaired areas, to better understand how the equipment/system
functions/operates. The subcommittee discussed the concepts regarding
potential risks and whether they could be exceptional if the project were delayed.
From his observations, potential catastrophic events can only occur in a few
places.
Mr. Ziemianek is confident that staff over the next 12 months can effectively
maintain the existing facility in its present condition until the improvements can
be made.
City Attorney Rapport commented on other project legal issues, and stated if
the contract were awarded, compliance with Proposition 218 is necessary. A
notice of the hearing concerning a sewer rate increase must be given to remain
within the 90-day bid period to accept the bid. A scenario that would not be
favorable would be if the bid is awarded, and notice is given to raise the rates
assuming that the rates would be increased to the bid amount of $56,000,000.
Because of the corresponding factors concerning the bid period, rate increase,
and notice of hearing, and other procedural bid requirements, construction could
not begin until the winter, and this would not be favorable. The primary focus for
tonight's discussion is to address the time period for the Iow bid that has already
run 45 days in order to comply with Proposition 218.
Joint Meeting of the City Council
And the Ukiah Valley Sanitation District
July 14, 2005
Page 5 of 8
A Kiewit Pacific representative addressed Option 3, and understands the
argument concerning the termination clause. However, he does not necessarily
agree with the probability of the second bidders' ability to be able to strengthen
their case and whether they would have recourse in the event Kiewit were
awarded the contract where Kiewit potentially ends up with change orders that go
down rather than up.
A general discussion followed regarding the "out clause" option on the City's part
and the associated concerns expressed from a legal standpoint, and whether an
addendum or alternative agreement could be created that strengthens/clarifies
the "out clause" that Kiewit agrees to.
Chief Deputy County Counsel Zotter commented on the legal issues regarding
contracts and potential causes of action with breach/violation thereof. The legal
contract issues basically pertain to offer and acceptance.
City Attorney Rapport is not sure whether Kiewit would be legally required to
accept such an agreement if the City awarded the bid to them, since they are
entitled to the contract as set forth in the bid document. The City could ask for
such an agreement, but Kiewit would not necessarily have to comply. The legal
risks lie in how the bidder stands by the contract, as written. It is essentially the
bidder's choice.
Mayor Ashiku reiterated that Option 1 or Option 2 is also available as alternate
to Option 3.
Councilmember McCowen inquired whether there is anyone other than the
contractor in a position to pursue a lawsuit, if Option 3 is chosen.
City Attorney Rapport stated a lawsuit could occur, but it is unlikely.
Councilmember McCowen inquired whether a bidder could waive any right to
initiate a lawsuit.
City Attorney Rapport acknowledged that this could happen.
MaYor Ashiku commented that Option 2 would allow staff in-house and the
subcommittee the opportunity to further review the design and determine what
changes may be necessary/conducive to the project as opposed to Option 3 that
has contract and/or other risk factors.
Board Member Crane commented on the decision-making process, and stated
the subcommittee reviewed certain criteria before looking at viable solutions.
Cost is a component of the project criteria.
Councilmember McCowen stated some allowance/thought can be given to
redesigning the plant plans as the process moves forward at the concurrence of
Joint Meeting of the City Council
And the Ukiah Valley Sanitation District
July 14, 2005
Page 6 of 8
the bid contractor. Option 3 rather implies that if a bid is awarded at the contact
price, it carries a prearranged understanding that the bid agreement would be
negotiated at a 10 or 15 percent reduction. Aisc, such a prearranged
understanding implies that if the target budget reduction is not achieved, the City
can walk away, . which may have legal repercussions. Alternatively, the bid could
be awarded to Kiewit with the understanding that a 60-day extension is part of
the agreement for the purpose of exploring value-engineering options. He
inquired if at the end of this time period, the City has the option of awarding the
bid at the contract price with the hope that the contractor would work with the City
as the process moves forward to achieve cost reductions, and whether this
approach is a legal option.
City Attorney Rapport stated the above-referenced "promise" would not likely
be enforceable.
Councilmember McCowen stated the matter pertains to a bid award rather than
a promise. The intent is to award the bid and hope that the bidder will work with
the City relevant to potential plan changes to achieve cost reductions as the
project moves forward.
City Attorney Rapport stated this type of agreement could be construed as an
appeal, which is not likely enforceable from a legal standpoint.
A summary of the project issues were discussed as follows prior to providing
direction:
.
.
,
.
!
.
Two bids are within two percent of one another. The other bidder may look
at what changes could have been made that contributed to their bid
coming in higher. If the project were reduced to eliminate those costs
items that happened to make their bid higher, does this say, in effect, that
this bidder was given a lesser opportunity to make those same changes
themselves in order to benefit. This matter may have potential legal
ramifications.
Consider the option of not rejecting the bid from Kiewit and request the 60-
day extension to allow time to decide whether suitable changes are
necessary.
Award the contract to Kiewit and hope to be able to negotiate necessary
changes that are found. Language in the contract provisions allow for
negotiating change orders.
Consider Proposition 218 noticing issue concerning the 60-day extension
option in conjunction with the 45-day time period that has already run.
Allow time for legal staff to evaluate options concerning the two bidders.
Consider all risks involved concerning the bids and project needs relevant
to making an appropriate decision.
Review value-engineering proposals made by design consultant in terms
of cost reductions and whether the results were realistic.
Joint Meeting of the City Council
And the Ukiah Valley Sanitation District
July 14, 2005
Page 7 of 8
.
.
Consider all change orders and potential cost overruns and meet in 20/30
days.
Consider the tight time line for construction schedule and project phasing.
It was the consensus of the Ukiah City Council and the Board of Directors of the
Ukiah Valley Sanitation District to request a 60-day extension from Kiewit on their
bid to allow for value-engineering and design change options.
3. PUBLIC EXPRESSION
No discussion of this agenda item.
4. ADJOURNMENT OF JOINT MEETING
There being no further business, the meeting was adjourned at 6:13 p.m.
Cathy L:flawadly, Rec(~rding Secretary
Joint Meeting of the City Council
And the Ukiah Valley Sanitation District
July 14, 2005
Page 8 of 8