HomeMy WebLinkAboutMead & Hunt 2019-02-13; Amendment 1 2020-03-05c UNG. I$►`I-IV(- I
CITY OF UKIAH
AMENDMENT 1
TO
PROFESSIONAL SERVICES
CONTRACT #1819164 — PREPARATION OF STAND-ALONE
AIRPORT LAND USE COMPATIBILITY PLAN
This Amendment No. 1, entered on March 5, 2020, revises the Agreement for
Professional services dated February 13, 2019 between the City of Ukiah and Mead &
Hunt to prepare a stand-alone Airport Land Use Compatibility Plan.
This Amendment No. 1, as per Exhibit 1:
1) Amends the Scope of Services.
2) Adds an additional dollar amount of $30,000, for a revised total contract amount
of $160,000.
3) Extends the deadline for the completion of the work to July 31, 2020.
Except as expressly amended by this Amendment, all other terms remain unchanged and
in full force and effect.
IN WITNESS WHEREOF, THE PARTIES HAVE EXECUTED THIS
AMENDMENT ON THE EFFECTIVE DATE:
MEAD & HUNT �/
BY: r' aa�o a4.
MITCHELL R. HOOPER
CITY OF UKIAH
BY:
/
SAGR %� ACOMO, CITY MANAGER
ATTEST
t,
BY:
DATE: March 6, 2020
DATE: 0 ci
{ DATE: 3 - 2-02-9)
KRISTINE LAWLER, CITY CLERK
Mead
60. I lunt
February 18, 2020
Craig Schlatter
Director of Community Development
City of Ukiah
300 Seminary Ave.
Ukiah, CA 95482
Exhibit 1
Project Name: Ukiah Municipal Airport Land Use
Compatibility Plan (ALUCP)
Project Location: Ukiah Municipal Airport (UKI)
Project number: 2112200-190459.01
Mead & Hunt Manager: Maranda Thompson
Subject: Amendment No. 1 - Expanded Technical Justification and Local Coordination
Dear Mr. Schlatter:
The above -referenced PROJECT requires an Amendment. The work covered under this Amendment
is in addition to the Scope of Services stated in the original CONTRACT between the CLIENT (City
of Ukiah) and the CONSULTANT (Mead & Hunt, Inc.) dated 2/13/2019.
The CLIENT agrees that the CONSULTANT shall provide additional professional consulting
services for the PROJECT as set forth in this Amendment and the CLIENT shall provide payment
for those services as provided for in this Amendment.
A detailed description of our understanding of the Amended PROJECT Scope of Services, Schedule,
and Compensation is provided below.
Reason for Amendment
The original CONTRACT reflected a streamlined PROJECT effort with a 12 -month schedule,
$130,000 budget (including $5,000 contingency), six site visits, and six hours for conference calls.
Additional effort by the CONSULTANT has been required to address strong divergent viewpoints
of the Technical Advisory Group established for this PROJECT. This Amendment documents the
Additional Tasks Completed (Not in Original Scope), Additional Tasks Pending (Not in Original
Scope), and Tasks Pending (In Original Scope). This Amendment reflects a PROJECT budget increase
of $30,000 and extension of the PROJECT schedule of up to six months.
UKI.ALUCP.Amendment No 1.200218
Mr. Schlatter
2/18/2020
Page 2
Background
A Technical Advisory Group (TAG) was composed with membership from the City of Ukiah, County
of Mendocino, and Mendocino County Airport Land Use Commission (ALUC). The purpose of the
TAG was to provide input to airport land use compatibility policies and feedback on project
deliverables. From the beginning, members of the TAG had strong divergent viewpoints on the
formulation of the draft compatibility zone boundaries and policies. This circumstance has required
an expanded effort by the CONSULTANT, beyond the work included in the original Scope of
Services, to analyze each disputed topic, describe advantages and disadvantages, and provide options
for potential resolution. These areas of disagreement, which have required additional effort by the
CONSULTANT, also necessitate extension of the PROJECT schedule and increase in the PROJECT
Budget.
The purpose of this Amendment is three -fold, as follows:
1. To document the additional work effort completed to date to address opposing comments of
TAG. This Amendment acknowledges that the existing PROJECT task budgets were reallocated
to cover this additional work that was not included in the original Scope of Services but has
since been completed. See "Additional Tasks Completed (Not in Original Scope)" below.
2. To document the tasks remaining to complete the PROJECT. Most of these tasks are those
included in the original Scope of Services but have yet to be completed. Since the existing
PROJECT Budget was reallocated to other additional tasks specified under Item 1 above,
additional budget is required to complete pending tasks. See "Additional Tasks Pending (Not in
Original Scope)" and "Tasks Pending (In Original Scope)" below.
3. To document the additional budget needed to complete the PROJECT. The Amended Budget
considers the additional work completed, additional work pending, original work pending, and
the reallocation of existing Project Task Budgets. This Amendment reflects a budget increase of
$30,000.
UKI.ALUCP.Amendment No 1.200218
Mr. Schlatter
2/18/2020
Page 3
Amended Scope of Services
The Scope of Services for the PROJECT is amended as follows:
Additional Tasks Completed (Not in Original Scope)
1. Expanded coordination effort to work through project elements with the City, County, and
TAG.
2. Modeling noise contours for CalFire Peak Day activity to reflect seasonal variations in UKI
operations.
3. Research related to the factors involved in setting the existing and future Runway 15 end and
landing threshold.
4. Analysis related to the possible establishment of a "blended" Runway Protection Zone (RPZ) at
the north end of the airport.
5. Analysis related to the advantages and disadvantages of maintaining the parcel -based composite
compatibility zones or using the safety zones from the California Airport Land Use Planning
Handbook (Handbook).
6. Analysis related to adjusting the draft compatibility zones south of UKI in recognition of the
high terrain to the west which affects the southerly traffic pattern.
7. Analysis related to the possible establishment of an "Urban Overlay Zone" in recognition of
existing land use patterns.
8. Expanded effort to prepare the administrative drafts of the ALUCP for City, County, and TAG
review.
Additional Tasks Pending (Not in Original Scope)
1. Project management for up to six additional months.
2. TAG#4 conference call to obtain feedback on the Administrative Draft ALUCP.
Original Tasks Pending (In Original Scope)
1. Preparation of the Public Draft ALUCP based on TAG comments. Assumes no major change
to the intent of the draft policies.
2. Completion of the draft CEQA document.
3. Participation in Joint City/County Planning Commission meeting.
4. Participation in Joint City/County Elected Officials meeting.
5. Preparation of responses to public comments and addendum to draft ALUCP.
6. Participation in ALUC adoption hearing.
7. Preparation of Final ALUCP.
UKI.ALUCP.Amendment No 1.200218
Mr. Schlatter
2/18/2020
Page 4
Amended Schedule
CONSULTANT proposes the following revised date to complete the work for this PROJECT:
• Approximate end date: 7/31/2020 (increase of up to 6 months to the original contract
schedule).
Schedule dependent upon coordination between the City and County for meeting scheduling.
PROJECT MILESTONES
ORIGINAL REVISED
(2019) (2019/2020)
Tasks Completed
Notice to Proceed February 2019 2/25/19
ALUC Meeting #1 Kickoff April 2019 April 2019
TAG CaII #1 Background Paper May 2019 June 2019
TAG CaII #2 Policy Paper June 2019 July 2019
TAG Call #3 Compatibility Zones/Criteria (Additional) NA October 2019
ALUC Meeting #2 ALUCP Update July 2019 November 2019
Draft ALUCP (City Review) August 2019 December 2019
Draft ALUCP (County Review - Additional) NA January 2020
Draft ALUCP (TAG Review - Additional) NA February 2020
Tasks Pending
TAG Call #4 Draft ALUCP (Additional) NA February 2020
Draft ALUCP and CEQA (Public Review) October 2019 March 2020
ALUC Meeting #3 Draft ALUCP/CEQA Circulation October 2019 NA
City/County Meeting #1 Planning Commission November 2019 April 2020
City/County Meeting #2 Elected Officials November 2019 April 2020
ALUC Meeting #4 ALUCP Adoption December 2019 May 2020
Final ALUCP December 2019 June 2020
Amended Compensation
Form of compensation for work under this Amendment will be in accordance with the Terms and
Conditions of the existing CONTRACT. The City of Ukiah will pay Mead & Hunt an increase of Thirty
Thousand Dollars ($30,000) for the work performed under this Amendment. This Amendment
results in a revised total contract amount of One Hundred Sixty Thousand Dollars ($160,000) for the
PROJECT. A budget breakdown is included as Attachment 1 to this Amendment.
Amended Responsibilities of (City of Ukiah)
In addition to those responsibilities listed in the original CONTRACT and previous amendments (if
applicable), this Amendment is based on City of Ukiah performing or providing the following:
• Public circulation and State Clearinghouse submittal of the Draft ALUCP and associated CEQA
document.
• Continued coordination with County regarding meeting schedules.
UKI.ALUCP.Amendment No 1.200218
Mr. Schlatter
2/18/2020
Page 5
Authorization for Amendment
The Amended Scope of Services, Schedule, and Compensation stated in this amendment are valid for
a period of fourteen (14) days from date of submission. If authorization to proceed is not received
during this period, this amendment may be reviewed and modified by Mead & Hunt.
Signatures of authorized representatives of City of Ukiah and Mead & Hunt, Inc. shall amend the
existing Agreement (original CONTRACT and all previous amendments, if applicable) between the
two parties, and receipt of one signed copy shall be considered authorization to proceed with the work
described in this Amendment. All services will be performed in accordance with the Terms and
Conditions of the original CONTRACT and amendment(s), if applicable. If a signed copy of this
Authorization is not received by Mead & Hunt, Inc. within fourteen (14) days from the date of
issuance, Mead & Hunt, Inc. may stop work on the above services.
Respectfully submitted by,
MEAD & HUNT, Inc.
Maranda Thompson
Project Manager
Attachments:
1 — Amended Budget Cost Breakdown
2 - Mead & Hunt, Inc. 2020 Billing Rate Schedule
UKI.ALUCP.Amendment No 1.200218
Attachment 1
Ukiah Municipal Airport Land Use Compatibility Plan (ALUCP)
Amendment No. 1 Budget
2/18/2020
WORK PLAN
Orginal Amendment No. 1
Budget Budget
TOTAL Summary of Additional Tasks (as detailed above)
Element 1: Project Management,
Coordination, and Meetings
$ 29,810 $ 7,000 $ 36,810 6 -month project extension (1 hour/month)
TAG#4 conference call (2 -hour call plus 2 hours preparation)
Joint PC meeting (2 -hour meeting, 2 hours for travel, 2 hours preparation, 1 staff person, plus expenses)
Joint Electeds meeting (same as PC meeting)
ALUC meeting (same as PC meeting)
Element 2: Data Collection and Compilation $ 24,674 $ 2,400 $ 27,074 CalFire Peak Day noise contours and related data compilation
Element 3: Draft ALUCP Preparation
$ 35,320 $ 8,600 $ 43,920 Second administrative draft (County Review)
Third administrative draft (TAG Review)
Fourth administrative draft (Public Review)
Element 4: Environmental Documentation $ 17,266 $ - $ 17,266 None
Element 5: Review and Adoption
Element 6: Additional Services
$ 17,930 $ 12,000 $ 29,930 Response to public comments
Addendum to draft ALUCP
Final ALUCP
$ 5,000 $ 5,000 None
TOTAL $ 130,000 $ 30,000 $ 160,000
Attachment 2
MEAD & HUNT, Inc.
California Standard Billing Rate Schedule
Effective January 1, 2020
Standard Billing Rates
Clerical $82.00 / hour
Technical Editor $115.00 / hour
Senior Editor $168.00 / hour
Registered Land Surveyor $130.00 / hour
Accounting, Administrative Assistant $109.00 / hour
Technician I, Technical Writer $101.00 / hour
Technician II, Surveyor - Instrument Person $117.00 / hour
Technician III $125.00 / hour
Technician IV $144.00 / hour
Senior Technician $174.00 / hour
Engineer I, Scientist I, Architect I, Interior Designer, Planner I $131.00 / hour
Engineer II, Scientist II, Architect II, Interior Designer, Planner II $142.00 / hour
Engineer III, Scientist III, Architect III, Interior Designer, Planner III $151.00 / hour
Senior Engineer, Senior Scientist, Senior Architect, Senior Interior Designer,
Senior Planner, Senior Economist $178.00 / hour
Project Engineer, Project Scientist, Project Architect, Project Interior Designer,
Project Planner $205.00 / hour
Senior Project Engineer, Senior Project Scientist, Senior Project Architect, Senior
Project Interior Designer, Senior Project Planner $241.00 / hour
Senior Associate, Principal, Senior Client/Project Manager $324.00 / hour
Expenses
Geographic Information or GPS Systems $100.00 / day
Total Station Survey Equipment $110.00 / day
Charges for other equipment may appear in a proposal
Out -Of -Pocket Direct Job Expenses cost plus 15%
Such as reproductions, sub -consultants / contractors, etc.
Travel Expense
Company or Personal Car Mileage $ IRS rate / mile*
* the current IRS rate as of Jan. 2020 is: 57.5 cents per mile
Air and Surface Transportation cost plus 15%
Lodging and Sustenance cost plus 15%
Billing & Payment
Travel time is charged for work required to be performed out -of -office. A minimum of two hours will be billed for
any work out -of -office.
Invoicing is on a monthly basis for work performed. Payment for services is due within 30 days from the date of
the invoice. An interest charge of 1.5% per month is made on the unpaid balance starting 30 days after the date
of invoice.
This schedule of billing rates is effective January 1, 2020, and will remain in effect until December 31, 2020, unless
unforeseen increases in operational costs are encountered. We reserve the right to change rates to reflect such
increases.