RESOLUTION NO. 83- 33
RESOLUTION OF THE CITY COt~CIL OF THE CITY OF
UKIAH APPROVING USE PERMIT NO. 83-11, UKIAH GREEN
WHERF~S, the 2.6 acres encompassed by Ukiah Green is zoned PD, Planned
Development, and
IsHE~S, the PD, Planned Development zone requires a use permit to be
reviewed and approved by the Planning Commission and the City Council prior
to development taking place within that zone, and
WHEREAS, on October 13, 1982 the Planning Commission approved Use Permit
83-11 with 18 condit ions, and
WHEREAS, a Negative Declaration for the rezoning of the property was
approved in November 1979.
NOW THEREFORE BE IT RESOLVED that Use Permit No. 83-11 is approved
subject to the following conditions:
1. Water and sewer improvement plan to be approved by the City Engineer and
include mains in the new street through the project.
2. On-site fire hydrant Rich #76 or equal to be provided.
3. Sound attenuation measures be taken to insure noise levels do not exceed
the maximum allowable levels to the approval of the Building Inspector.
18 4. Dedication of a 50 ft. public right-of-way to provide access and utilities
19
2O
21
22
23
24
25
26
27
28
to the southern property line. Said right-of-way be constructed to City
standards for 50' street including curb, gutter, sidewalk, paving, street
lights and drainage by applicant to approval of Director of Public Works.
5. Submit application and process parcel map to eliminate property lines
through development.
6. Existing sewer laterals that are not used should be abandoned by the City
at the owner's expense.
.~
7. Street improvements, including curb, gutter,sidewalk, paving and drainage
on Observatory Avenue be constructed to the approval of the Director of
Public Works.
-1-
4
$
6
7
8
9
10
11
12
15
14
15
16
17
18
19
20
21
22
2~
24
25
26
27
28
8. 50% of on-site drainage to be taken to Doolin Creek. A drainage easement
shall, be taken through storm drains or in pipes under sidewalks to face
of curb.
9. On-site paving to be a minimum 2" of asphaltic concrete of a 6" aggregate
base.
10. Undergrounding of utilities required at owner's expense, including
necessary street lights along street frontages.
11. Capital Improvement fees as set forth by the Director of Public Works be
paid by the applicant.
12.Trash collection facilities be aesthetically screened from view.
13. Any roof mounted air conditioning apparatus be aesthetically screened
from view.
14. All landscaping be irrigated by an automated irrigation system and
maintained in a neat, weed-free manner. A landscaping plan be approved
by the Director of Planning prior to placement.
15. Standard Conditions 1-9.
16. Improvement plans shall be prepared by a Civil Engineer at the developer's
expense and approved by the Director of Public Works.
17. A density bonus of seven units is granted pursuant to State statute
allowing a total of 38 units for the project.
18. Ail setbacks shall be as depicted on the approved site plan.
PASSED _A~4D ADOPTED this 3rd day of November, 1982 by the following roll
call vote'
AYES' Councilmembers Feibusch, Kelley, Myers, Riley
NOES' None
ABSENT. Councilmember Hickey