HomeMy WebLinkAboutSHN Consulting Engineers & Geologists, Inc. 2016-01-05; Amendment 1 2016-05-13/06 4/1-19 )
CITY OF UKIAH
AMENDMENT NO. 1
TO AGREEMENT FOR PROFESSIONAL CONSULTING SERVICES
DATED JANUARY 5, 2016
TERMS AND CONDITIONS
All terms and conditions of the Agreement for Professional Consulting Services dated
January 5, 2016 shall remain in force and effect except as modified by this first
amendment.
AUTHORIZATION
Upon execution of this amendment, service provider is authorized to provide the service
described under the Scope of Additional Work identified in this Amendment No. 1.
SCOPE OF ADDITIONAL WORK
Work authorized by this amendment shall include that work described in the
Phases 1 and 2 Additional Work also referred to as Attachment 1. A copy of said work is
included in this first amendment,
COMPENSATION
Compensation for the performance of the additional work shall be made on a time and
expense basis at Consultant's customary fees. Expenses shall not exceed a maximum
total cost of $39,654
SHN CONSULTING ENGINEERS CITY OF UKIAH
AND GEOLOGISTS, INC.
BY:
AL
4 BY:
Si SANGCOMO
CI Y MANA ER
/1" f/e7,-;44,e
PRINT NAME DATE
DATE
Amendment No. 1 to Agreement for
Professional Consulting Services
`rte_
A)1'
9t7' J1
Pro ect Title:
Client:
Client Contract/PO #:
SHN Job Number:
Project Modification Agreement
North State Street Sewer Main Im.rovement Pro'ect, S•ecfication No. 14-04
City of Ukiah
Agreement dated January 5, 2016
415080
Project Manager:
Change No.:
Tom Herman
1
Project requirements or conditions encountered indicate that the Scope of Services included in this Project must
be revised. CLIENT and SHN hereby agree that the Project Scope of Services, Schedule, and/or Budget shall
be revised as described below.
1
Scope of Services Change:
Client has requested an increase in the Construction Management and Inspection Services
e
Project from 30 calendar days to 70 calendar days. The additional cost for these services isa proportiperiod for onal
increase based upon the requested time extension. The original cost not to exceed of $29,815 will be increased
by 233% to a cost not to exceed $69,469.
Impact To:
Initial Budget: $29,815
Current Budget: $29,815 (Reflecting Prior Changes)
Budget Change: $39,654 (Addition or Reduction +/-)
Revised Budget: $69,469
Initial Schedule: 30 (days)
Current Schedule: 70 (Reflecting Prior Changes)
Schedule Change: 40 (addional days)
Revised Schedule: 70 (days)
Other:
Individuals Endorsing Change:
Thomas M Herman
SHN Project Manager
Thomas Hunt
SHN Protect QA/QC
X
(signature)
(signature)
14 r
A�thzation to Proc d with Change:
Consuttl ngin &
Geologists, SWN g , Inc.
Client
Date: � /� Date: /(