HomeMy WebLinkAboutEnviromental Science Associates 2009-12-21; Amendment 1 2010-06-24Environmental Science Associates ESA Amendment No. I
Task No. 09418
Amendment to Professional Services Agreement ESA Project
www.esassoc.com
7ZA
THIS AMENDMENT ("Amendment") is made and entered into this day of June, 2010, by and between
Environmental Science Associates (hereinafter ESA), a California corporation and the City of Ukiah, a general law
municipal corporation ("City") and amends the parties' Agreement, dated the 21s` day of December, 2009
(Original Agreement).
RECITALS
ESA and City previously entered into an Agreement for professional services.
The parties now wish to enter into an Amendment to said Agreement under which ESA will perform
additional services for Client.
TERMS AND CONDITIONS
Scope of Work
The additional Scope of Work covered by this Amendment is shown in Attachment A, which is attached to
this document and made a part of this Amendment.
2. Price
Payment to ESA under this Amendment, including expense reimbursement, shall not exceed $ 34,615 .
(W-Trans cost $30,100 plus 15% mark-up for all non-labor expenses = $34,615.1
Total new Contract Amount is $ 403,780.
Effect of Amendment
Except as amended herein, the parties' Original Agreement shall remain in full force and effect.
IN WITNESS THEREOF, the parties hereto have executed this Amendment by their duly authorized agents as of
the day and year first above written.
Environmental Science Associates
225 Bush Street, Suite 1700
San Francisco, CA 94104
: !L d~ By: ~n p ® k a
By
J J (Signature) (Dat) (Signature) (Date)
Name: _)~C L V)C kY6-VW
(Printed Name)
Name: i 1_C
(Printed Name)
Title: l a nel Y
Title: UA-% g q ~a /
ATTACHMENT A
Rage 1 of 2
Ukiah Walmart Expansion EIR - Additional Tasi€s for Traffic Section
May 10, 2010
The following tasks will be added to W=Trans' scope of work to complete the Traffic & Circulation
section for the Draft EIR on the Ukiah Walmart Expansion project. These tasks are based on
discussions with ESA, the City of Ulklah and the applicant representatives.
1. Weekend Traffic Check Weekend peak hour turning movement traffic volumes will be
collected at the intersection of Talmage Road/Airport Park Boulevard. The volumes will be
used to confirm that the weekend peak conditions are lower than the weekday p.m. peak hour
traffic volumes. The resulting conditions will be documented in the Existing Conditions section.
(Budget = $6100)
2. Walmart Trip Generation Rate Check - Existing traffic volumes collected in and around the
Walmart will be reviewed to estimate the existing vehicle trip generation rate for the existing
Walmart store. The purpose of the review is to justify the use of standard ITE trip generation
rates for the expansion rather than the 'development and use of custom trip generation rates.
The results of this analysis will be documented in the Project Vehicle Trip Generation section of
the report. (Budget = V00)
3. Additional Fully Zoned Future Scenarios - An additional Future traffic scenario will be
developed and analyzed. The current Future Scenario assumes the current growth rate for the
remaining vacant land in the Redwood Business Park. The additional scenario will maximize the
density of the remaining vacant land. The "Future with Fully Zoned RBP" traffic volumes Will be
developed by adjusting the UVAP model. results as necessary to produce the appropriate vehicle
trip generation to/from the Redwood Business Park-. Walmart expansion traffic volumes will
then be added to this additional, .future conditions scenario. Traffic conditions under these two
scenarios will be analyzed to determine intersection level of service conditions, queuing
conditions, freeway mainline LOS and related traffic operations for the study area which were
evaluated under other scenarios. Impacts: will be identified based on the established thresholds
and mitigation measures determined for those conditions which exceed the standards. The
results will be documented in the traffic section of the DE1R. (Budget = $7,600)
Based on this amendment, scenarios to be included in the Traffic & Circulation Section
include (bold scenarios have been added as part of this amendment).
Existing
Baseline
e Baseline plus Project
® Future with Current RBP Growth
Future with Current UP Growth plus Project
Future with Fully Zoned RBP
Future with fully Zoned RBP plus Project
ATTACH ENT A
Page 2 of. 2.
,LL.
4. Conditions with Discount Club Scenarios including a 148,006 quart foot discount Club use
within the_ Redwood Business Park area will be developed and analyzed. "Traffic conditions
under these scenarios will be analyzed to determine intersection level of service conditions,
queuing conditions, freeway mainline LOS and related traffic operations for the study area which
were evaluated under other scenarios. Impacts will be identified based on the established
thresholds and mitigation measures determined for those conditions which exceed the
standards. The results will be documented in the traffic section of the DEIR separate from the
conditions without the. Discount Club, organized .in a manner acceptable to the City. These
scenarios include:
• Baseline with Discount Club: The scenario will include the three previously identified projects,
Koller Quarry, as well as this 14$,000 square-foot liscount Club,
a Baseline with Discount Club plus Project
Future with Current RBP Growth including Discount Club: Similar to the Current RPB Growth
conditions, but replaces 14$,00.0 square feet of the center with a Discount Club use.
® Future with Current RBP Growth including Discount Club plus Project
Future with Fully Zoned RBP including Discount Club: Similar to the Fully Zoned RPB. Growth
conditions, but replaces 14$;000 square feet of the center with a Discount Club use,
® Future with Fully Zoned RBP including Discount Club plus Project.
(Budget = $19,400)
These (bold) scenarios have been added as part of this amendment.
• Baseline with Discount Club
Baseline with Discount Club plus Project
• Future with Current RBP Growth including Discount Club
• Future with Current RBP Growth including Discount Club plus
Project
Future with Fully Zoned RBP including Discount Club
® Future with Fully Zoned REP including Discount Club plus Project
5. Additional Response..to Staff Comments Due to the additional scenarios, 6 hours of response
to staff comments on the draft traffic study have been added. (Budget - $900)
b. Additional Response to Public Comments- Due to the additional scenarios, 8 hours of
response, to public comments on the DEIR. traffic issues have been added. (Budget = $.1,200)
Budget - The total additional budget request is $30,100 which would increase the contract amount
from $57,540 to $$7;600.