HomeMy WebLinkAboutR.W. Beck, Inc. 2007-03-21; Amendment 1 2008-08-27August 27, 2008
Mr. Mel Grandi
Utilities Director
City of Ukiah, Electric Utility
411 West Clay Street
Ukiah, CA 9548
Subject: Additional Engineering Services for Gobbi Substation Relocation
Dear Mr. Grandi:
As previously discussed, the current plans for the City of Ukiah (City) substation upgrade have changed
since the original Scope of Services was prepared. The revised plan includes a new substation on a new
site instead of a modification to the existing site. Therefore, we are providing a modification to the
original Scope of Services.
The new substation would include three 20/26.6/33.3//37 MVA transformers, four 115 kV circuit
breakers, 115 kV steel structures and bus work, and a prefabricated control building. The control building
would house the 12 kV switchgear, protective relaying, DC battery system, and communication
equipment. The 12 kV switchgear will consist of three 2000 A main buses, three 2000 A main breakers,
two 2000 A bus tie breakers, and twelve 1200 A feeder breakers. The estimated dimensions of the site
will be 250' x 200'. The substation will be enclosed by a seven foot fence with two 20-foot access gates
opening on to Orchard Avenue.
Additionally, in order to integrate the new substation into the existing system and relieve the current
underground congestion along Orchard Avenue, the proposed scope additions include distribution design
along Orchard Avenue and Ford Street and along Gobbi to the railroad.
Other services offered to provide benefit to the City during the project include the California
Environmental Quality Act (CEQA) Environmental Process and assistance in procuring, evaluating and
installing a radio link from the Hydro Plant to the City Hall.
Scope of Services
The proposed additional Scope of Services would include the following:
Additional Substation Engineering Services
Additional work relating to expanding the general arrangement
Additional work relating to expanding the electrical plan and sections
Additional work relating to the conduit plan and circuit lists
Additional work relating to the grounding plan and calculations
Additional foundation design and calculations
Development of site plan
Development of grading plan and details
Development of fencing plan and details
A masonry fence will be utilized for the perimeter of the substation.
Additional shop drawing review
131 Mir Parkway, Suite 300 Heudersonville.'IN 37075 Phone (615) 431-3200 Fax (615) 824-7570
Mr. Mel Grandi
August 22, 2008
Page 2 of 5
Demolition coordination of the existing site
Transmission line design for extension of existing line to the new site
The additional services assumes existing line will extend due west with 2-3 additional structures
required.
11 Geotechnical investigations for new site
Two additional site visits during construction
CQA Environmental Services
R. W. Beck will retain a Subconsultant to develop the CEQA process. Based on review and discussions,
the City and R. W. Beck has selected LACO Associates as the CEQA Subconsultant. The Subconsultant
will work with the City and R. W. Beck to develop an initial Study. This service assumes a Mitigated
Negative Declaration would be the appropriate document for the proposed project. The Scope of Services
provided by the Subconsultant is enclosed as Exhibit A. R. W. Beck will provide task oversight and
technical information for the Study, including the following:
Provide detailed project management plan, including Scope of Services, staffing plan, project budget,
schedule, risk assessment, and communications plan
Conduct weekly project team action-item review meetings through teleconference call
Maintain and distribute detailed action-item list
Prepare monthly progress reports, including summary of accomplishments, progress to completion of
milestones and deliverables, comparison of current and cumulative actual and budgeted labor and
costs, and evaluation of issues that could negatively impact project completion
Prepare and distribute agendas and minutes from project meetings
Coordinate project team, staffing and subcontractors
Provide monthly project updates with the City via teleconference
Provide technical assistance as needed for CEQA checklist
Provide drawings and maps needed for CEQA checklist
Provide technical assistance to the City, as needed, to define the substation technical issues for the
process
Underground Distribution Design
R. W. Beck will provide detailed design for the underground distribution design along Orchard Avenue
from the substation site to the Ford Street intersection and from the substation along Gobbi to the west
side of the railroad tracks. The design will relieve congestion in the existing duct bank and manhole
system, and provide interconnections to the new substation. Tasks for the design will include the
following:
Field topographical survey from substation to Ford Street along Orchard Avenue and from substation
to west of railroad tracks along Gobbi and from substation to Talmadge Street along Orchard
Mr. Mel Grandi
August 22, 2008
Page 3 of 5
Survey will be limited to above grade facilities. The City should provide invert elevation and
modeled detail of underground City and facilities.
Survey and processing services for lot line adjustment for new site
Survey and processing services for abandonment of existing utility easement on substation property
Develop plan view of modifications
Develop profile view of modifications
11 Develop switchgear and manhole details
Develop specifications for inclusion into the Construction Contract for the project
Develop detailed one-line drawings for integration of existing UG radials, switchgear and
transformers with new facilities.
Develop duct bank details with duct cross-section drawings, as required
Perform cable ampacity and pulling calculations
Develop sectionalizing and protection scheme for the area being modified with this project
radio System for Hydro Plant
R. W. Beck will assist the City to procure a microwave point to point radio system for the
communications to the Hydro Plant from City Hall. The assistance will be in the form of soliciting
quotations from potential vendors of this type of equipment, evaluating the quotations and preparing
performance installation specifications and drawings. Assistance will be limited to the radio equipment
and will not include the network engineering for the connections or tower design or modifications.
Deletion of Distribution Line Design
(4.25-miles of Overhead Construction from Substation to Hydro Plant)
Based on our discussions, the City has elected to remove this project from the Capital Improvement Plan.
The revised Scope of Services include a deduction for the engineering included in the original Scope of
Services minus services provided to date.
On-site Construction Management Services (Optional)
R. W. Beck can provide on-site construction management, if requested. This would include an on-site
field representative for the duration of the on-site activities. Construction Management Services provided
during construction would include:
Providing one full-time, on-site construction manager/inspector for the duration of project
construction (for budgeting purposes assumed to be six months)
Assisting Ukiah in coordinating and hosting a pre-construction meeting
Observing construction to review conformance of construction with the contract documents and intent
of design
Periodically review delivery of materials and its impact on the project schedule
Providing day-to-day information on the status of construction and the project schedule
Mr. Mel Grandi
August 22, 2008
Page 4 of 5
Observing site operations; foundation construction; equipment placement; structure erection;
subsurface facilities; and contractor field testing, start-up, and final cleanup
Preparing and maintaining records to document receipt of Ukiah furnished material (if applicable),
construction activities, contractor's project staffing by crafts, construction progress, and meeting
minutes
Observing tests and checks throughout the construction period, such as concrete cylinder tests, soil
compaction test, survey checks, and testing of electrical and mechanical equipment and systems
Maintaining records of construction changes and check that the contractor does likewise, so that after
the project's completion, drawing revisions can be made to provide accurate conformed-to-
construction record drawings
Attending project meetings held by the contractor
11 Responding to RFIs and questions that arise during construction
Reviewing construction contractor requests for payment
11 Reviewing construction contractor change requests
Providing monthly project progress reports on budget and schedule performance, as well as any
obstacles and recommended solutions
Fee for Additional Services
The additional Scope of Services presented herein will be provided for the not-to-exceed amount as
indicated in the table below. R. W. Beck shall not be required to furnish additional services or incur
additional expenses above the total project fee without written authorization and additional funding from
the City of Ukiah. This proposal will remain valid for 45 days from the date first written above.
Additional Substation Ei glnoo[,ng 30)r,,O s $ 110,065
CEQA Environmental Services
$ 48,337
Underground Distribution Design
$ 105,432
Radio System for Hydro Plant
$ 7,539
Additional Services Total:
$ 271,373
Adjustment to Task 8 - Hydro Circuit
- $ 99,489
Total Adjustment to Original Contract
$ 171,884
Original Contract
$ 490,287
Total Amended Contract
$ 662,171
Optional Construction Management (estimated)
$ 265,000
Mr. Mel Grandi
August 22, 2008
Page 5 of 5
If the proposed services and fee meet with your approval, please authorize below and return one copy of
this agreement to my attention for our records. R. W. Beck will provide the services described herein
pursuant to the Professional Services Agreement between the City of Ukiah and R. W. Beck dated
March 21, 2007.
Thank you for the continued opportunity to provide our services to the City of Ukiah.
Sincerely,
R. W. BECK, INC.
Anthony Hanson, P.E.
Project Manager
encl: Exhibit A - LOCA Associates Scope of Services
Authorization
CITY OF UKIAH
Signed
Printed , .lane Chambers
Title Date September 29. 2008
Authorization o Optional Services
CITY OF UKIAH
Signed
Printed
Title
Date
R. W. BECK, INC.
Signed
Printed Keith Deaton
Title Principal and Regional Practice Manager
Date August 22, 2008
R. W. BECK, INC.
-4 .4
Signed t
Printed Keith Deaton
Title Principal and Regional Practice Manager
Date August 22, 2008